Morro Bay High School swimming pool

The new pool and support building was the first Measure D project to break ground. The 25-yard-by-35-meter swimming pool features 16 lanes and will have covered bleachers, exterior overhead lights and a LED scoreboard.

Morro Bay High School new pool

Images from the groundbreaking ceremony:

And construction under way:

The 3,815-square-foot support building has men and women’s locker rooms, office space, team meeting room, ample storage and a concessions kiosk.

Timeline: The groundbreaking ceremony was held on May 20, 2016. The project is anticipated to be completed in Fall 2017.

Construction cost: $4,700,000

Project team: KBZ Architects, Red Mountain Construction, Aquatic Design Group, Above Grade Engineering, BMA, Stork Wolfe & Associates, Thoma Electric, firma