Measure D Project Timeline

Construction Schedule as of April 24, 2017

The primary goal of the Measure D phasing and implementation plan is keeping each campus safe, fully functional and operational during construction and minimizing the impact to students, staff and neighbors. This schedule is subject to change.

Summer 2016
C.L. Smith Elementary School
Teach Elementary School
Winter 2017
San Luis Obisbo High School
  • Temporary Classrooms Phase 2
Summer 2017
Morro Bay High School
  • STEAM Complex Renovation (Building J -700 Wing)
  • Old Gym Renovation
All School Sites
  • New Phone System
C.L. Smith Elementary School
Teach Elementary School
  • Fire Alarm
Winter 2018
San Luis Obispo High School
Morro Bay High School
Summer 2018
San Luis Obispo High School
Morro Bay High School
Bellevue Santa Fe Charter School
Winter 2019
Morro Bay High School
  • Classroom Renovation (Building B 200 + 300 Wings)
Summer 2019
San Luis Obispo High School
  • Student Union and Classroom Building (Building 100 and Quad)
  • Renovate Building 300 into CTE facility
Summer 2020
Morro Bay High School
  • Renovate Classrooms and Library (Building C 400 Wing)
Summer 2021
Morro Bay High School
  • Student Union (Building A)
  • Renovate Wood and Metal Shop (Building D 500 Wing)
  • Renovate Plaza/Quad Area